S Curve Manhour- Baseline , Actual , Forecast

Hello Everyone,

 

I would like to make a S Curve in Primavera which shows Planned, Actual and Forecast S Curve.

The basis of S Curve to be manhours / Week.

Can S Curve in Primavera show % Planned per week as Lables like in Excel.

I want to calculate the S Curve which shows end of the Week Palnned % and Actuals (Not start)

Please guide me.

 

Regards

Jithin

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi Zoltan,

But that doesnt show % Planned Label per Week. 

 

It shows the curve but doesnt show the label.

Regards

Jitin 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

create a resource

assign the resource to the activities

assign the proper manhours to each activity

view show on bottom resource usage spreadsheet

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi Zoltan,

 

I am looking for a s curve which would be like this showing lables.

 

[[wysiwyg_imageupload:7355:]]

Z
Zoltan Palffy 👤 Member for 16 years 10 months

create a resource

assign the resource to the activities

assign the proper manhours to each activity

view show on bottom resource usage profile

select the cureves that you want to show

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts