Hello Everyone,
I would like to make a S Curve in Primavera which shows Planned, Actual and Forecast S Curve.
The basis of S Curve to be manhours / Week.
Can S Curve in Primavera show % Planned per week as Lables like in Excel.
I want to calculate the S Curve which shows end of the Week Palnned % and Actuals (Not start)
Please guide me.
Regards
Jithin
NOTHING show the label you did not ask for the label
Hi Zoltan,
But that doesnt show % Planned Label per Week.
It shows the curve but doesnt show the label.
Regards
Jitin
create a resource
assign the resource to the activities
assign the proper manhours to each activity
view show on bottom resource usage spreadsheet
Hi Zoltan,
I am looking for a s curve which would be like this showing lables.
[[wysiwyg_imageupload:7355:]]
create a resource
assign the resource to the activities
assign the proper manhours to each activity
view show on bottom resource usage profile
select the cureves that you want to show