Dear All,
I want to export my P6 file which is Resource and Cost loaded. I want to export the same file which includes both these data.
When i export the file by choosing project only option , the budgeted cost data is not displayed while importing this file .
Secondly, if i want to send the file which includes only activities and date, then how to hide the cost and resources.
Please explain both these methods. i would really appreciate
Thirdly, kindly explain the export options (project only and resource only)
Thanks
Regards,
Saqib
Thank You so much Alexandra.
God Bless You
Dear all
when i updating the project if i miss some thing then i want to go back few step . in Primavera P6 there are any sortcut option to go back 1,2,3 step.
please reply
thanks
Hello Muhammad,
1st question:
in the process of exporting an XER file, you will be able to edit the export template; add the necessary fields
2nd question:
it is not possible to hide cost and resources fields while exporting a project, whatever the export format is (XER, XLS, XML);
the workaround is to make a copy of your project: display the project screen, then copy and paste your project; then delete all resources and costs assignments from the project's copy; then export this file.
Alexandre