Export Cost and Resources

Dear All,

I want to export my P6 file which is Resource and Cost loaded. I want to export the same file which includes both these data.

When i export the file by choosing project only option , the budgeted cost data is not displayed while importing this file .

 

Secondly, if i want to send the file which includes only activities and date, then how to hide the cost and resources.

 

Please explain both these methods. i would really appreciate

 

Thirdly, kindly explain the export options (project only and resource only)

 

Thanks

 

Regards,

Saqib

M
Mohammad Zishan 👤 Member for 6 years 9 months

Dear all

 

when i updating the project if i miss some thing then i want to go back few step . in Primavera P6 there are any sortcut option to go back 1,2,3 step.

 

please reply 

 

thanks

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello Muhammad,

1st question:

in the process of exporting an XER file, you will be able to edit the export template; add the necessary fields

2nd question:

it is not possible to hide cost and resources fields while exporting a project, whatever the export format is (XER, XLS, XML);

the workaround is to make a copy of your project: display the project screen, then copy and paste your project; then delete all resources and costs assignments from the project's copy; then export this file.

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts