Percent Complete Changed when Baseline is inserted

R
Robin Reyes 👤 Member for 19 years 8 months

I am receiving an xer for the schedule update from the Contractor. The percent complete used for progress is the Cost Percent Complete. However, when I inserted the baseline into the schedule, the values on the Cost Percent Complete changes. When i removed the baseline, the Cost Percent Complete return to its original values. Does anyone knows the reason behind this? Thanks

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hello Zoltan

Thanks for this information. I recently moved to a new P6 database and forgot to change this default setting. Cost me hours to correct. Paul Harris also published this particular setting in the Admin.

Regards Johannes

Z
Zoltan Palffy 👤 Member for 16 years 10 months

goto 

Admin

Admin Preferences

Earned Value Tab

Then at the bottom under earned Value Calculations

make sure that the selection is Budgeted Values with current dates NOT PLANNED DATES

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts