I am receiving an xer for the schedule update from the Contractor. The percent complete used for progress is the Cost Percent Complete. However, when I inserted the baseline into the schedule, the values on the Cost Percent Complete changes. When i removed the baseline, the Cost Percent Complete return to its original values. Does anyone knows the reason behind this? Thanks
Percent Complete Changed when Baseline is inserted
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
just ask here or in linkedin and we will set you strainght.
Hello Zoltan
Thanks for this information. I recently moved to a new P6 database and forgot to change this default setting. Cost me hours to correct. Paul Harris also published this particular setting in the Admin.
Regards Johannes
goto
Admin
Admin Preferences
Earned Value Tab
Then at the bottom under earned Value Calculations
make sure that the selection is Budgeted Values with current dates NOT PLANNED DATES