% Complete

A
adab azeez 👤 Member for 9 years 10 months

While updating progress of my Project schedule, I am getting some values of unit% complete and physical % complete against certain value of schedule % complete, with each scheduling BUT..
why I am not getting performance % complete? Performance % complete is always zero which I am not expecting.

My duration type is Fixed duration and unit per time.
% complete type is duration.

Resources have certain prices and values.

Any help please ?

K
Kannan CP 👤 Member for 17 years 11 months

Hi,

For the performance %, you have to assign cost (as a weight factor or as per BOQ) in order to calculate the earned value.

BR

Kannan

A
adab azeez 👤 Member for 9 years 10 months

But in some of my project I am getting performance %. Literally I tried a lot but not able to understand the ligic behind this usage.
Thanks anyways.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts