While updating progress of my Project schedule, I am getting some values of unit% complete and physical % complete against certain value of schedule % complete, with each scheduling BUT..
why I am not getting performance % complete? Performance % complete is always zero which I am not expecting.
My duration type is Fixed duration and unit per time.
% complete type is duration.
Resources have certain prices and values.
Any help please ?
Hi,
For the performance %, you have to assign cost (as a weight factor or as per BOQ) in order to calculate the earned value.
BR
Kannan
But in some of my project I am getting performance %. Literally I tried a lot but not able to understand the ligic behind this usage.
Thanks anyways.
you have to use physical % complete