Units discrepancy for s-curve

Loaded my permitting with units to track an s-curve. Assigned 200 000 units across the activities. My report only has 194104 units in cumulative planned but cumulative estimate to & at completion indicates the 200 000 units loaded. No filters assigned that can trip me up and percent complete type set to units.

 

What could be the problem?

 

Running 18.8

Z
Zoltan Palffy 👤 Member for 16 years 10 months

under edit user preference

turn your decimal places on 

Time units tab

M
Morne Johann Beeslaar 👤 Member for 10 years 3 months

Thanks David, found it is exactly the problem.

 

Going to delete resources and reload as I guess this is the only fix.

D
David Kelly 👤 Member for 21 years 7 months

Primavera holds the numbers in two places, and they do get out of synchronisation.

You should check the units in both the “Activities” window and the “Resource assignment” windows

When you do a resource  profile/spreadsheet, the numbers come from one table, the Activity spreadsheet/profile and ALL earned value data comes from the other.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts