Dear All
i am working on epc project, our time schedule is not cost & resource loaded means only time schedule.
is there any ways/methods to determine monthly plan % ??
Dear All
i am working on epc project, our time schedule is not cost & resource loaded means only time schedule.
is there any ways/methods to determine monthly plan % ??
although I do not recommend this technique you can do it 2 ways
1 way is strictly tiime based and the other way is to calculate when actiivities were planned to FINISH vs when or is they have finished
send me your email address and I will show u how to do this
you can also use project tracker you can get a free trial here
https://www.willmer.co.uk/
Since you do not have any costs or resources, the monthly planned per cent complete is one month.