Monthly Planned progress from P6 without Cost/Resource

Dear All

i am working on epc project, our time schedule is not cost & resource loaded means only time schedule.

is there any ways/methods to determine monthly plan % ??

Z
Zoltan Palffy 👤 Member for 16 years 10 months

although I do not recommend this technique you can do it 2 ways

1 way is strictly tiime based and the other way is to calculate when actiivities were planned to FINISH vs when or is they have finished

send me your email address and I will show u how to do this 

you can also use project tracker you can get a free trial here

https://www.willmer.co.uk/

D
David Kelly 👤 Member for 21 years 7 months

Since you do not have any costs or resources, the monthly planned per cent complete is one month.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts