How to calculate earned value based on duration in P6 (Earned days or weeks)

Dear Team,

 

Clould you kindly hwo to implement in P6 to monitor the progress based on earned duration value. I read an artical with regard to this if you want i can send you all. Please send your e-mail.

Reagrds,

Riyas 

D
David Kelly 👤 Member for 21 years 7 months

Mohamed,

 

It is quite easy. You simply apply a resource to each activity, with the default units per time period (simplest if this is 1) This can be done in one pass with the multiple-assign function. 

Earned value can only come from resources in P6, but if the budget quantity is the same as the duration, then earned value becomes a function of Duration % complete.

Issues:

P6 only earns value from a baseline.  Be careful. 

If there are "real" resources in the plan, you will need to price these at zero in order for them not to be included in the earned value calculations.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts