Dear Team,
Clould you kindly hwo to implement in P6 to monitor the progress based on earned duration value. I read an artical with regard to this if you want i can send you all. Please send your e-mail.
Reagrds,
Riyas
Dear Team,
Clould you kindly hwo to implement in P6 to monitor the progress based on earned duration value. I read an artical with regard to this if you want i can send you all. Please send your e-mail.
Reagrds,
Riyas
Mohamed,
It is quite easy. You simply apply a resource to each activity, with the default units per time period (simplest if this is 1) This can be done in one pass with the multiple-assign function.
Earned value can only come from resources in P6, but if the budget quantity is the same as the duration, then earned value becomes a function of Duration % complete.
Issues:
P6 only earns value from a baseline. Be careful.
If there are "real" resources in the plan, you will need to price these at zero in order for them not to be included in the earned value calculations.