Date format reports

Hello,

I try to make a report and the date format is: Mon 8-1. I would like 1-8--2016.

In Primavera itself it shows OK.

How can I change the format in the report.

R
Rafael Davila 👤 Member for 22 years 3 months

If acceptable for you try exporting the report to Excel and change the cell format to whatever you need. You can go cell by cell, use range of cells or use ASAP Utilities [free for non-commercial users].

Convert Date Format photo Covert Date Format_zpsk1hbz8he.png

Good luck.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

almost any report can be reproduced in the data table where you can change the date format 

M
Mark Siemonsma 👤 Member for 9 years 7 months

Zoltan, thank you for your answer. This does however not work for the reports. There it does not use the user preferences

M
Mark Siemonsma 👤 Member for 9 years 7 months

Zoltan, thank you for your answer. This does however not work for the reports. There it does not use the user preferences

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts