Hello Dears;
When we do the monthly report, we usually send to the contractor a table showing the most important zones which have the activities of the project; showing in this table:
1- % Planned complete
2- % Actual complete
3- Variance; (Actual % - Planned %)
No problem with getting the actual %, my question is how to get the planned %
Please Help :)
Thank You,
Hi Nouraldi, Hope this will answer more on your questions.. https://www.planacademy.com/primavera-p6-schedule-percent-complete-guid… Good Luck!!!
Hi Sir,
The resources are loaded,
Actually i tried the same on another project, and the percentages for the WBS's were calculated
Is there any relation between kind of resource ( which i dont know what is it ) and the shedule % ?
Best Regards
Hi Nouraldi,
1. Yes, you got it.
2. Seems your schedule was not resource loaded?
Please let me know.
Hello sir;
Does this picture describe your answer?
and why the WBS has no planned (Schedule) Percent ?
or i should estimate it?
Thanks for your help :)
[[wysiwyg_imageupload:4480:]]
Hi Nouraldi,
To be able to show the % Planned Complete ( Schedule % Complete in Primavera ), you should maintain and assign baseline to your current schedule.
Hope this helps.