% Planned complete

Hello Dears;

When we do the monthly report, we usually send to the contractor a table showing the most important zones which have the activities of the project; showing in this table:

1- % Planned complete

2- % Actual complete

3- Variance; (Actual % - Planned %)

No problem with getting the actual %, my question is how to get the planned %

Please Help :)

 

Thank You,

N
Nouraldin Alqudsi 👤 Member for 9 years 8 months

Hi Sir,

The resources are loaded,

Actually i tried the same on another project, and the percentages for the WBS's were calculated

Is there any relation between kind of resource ( which i dont know what is it ) and the shedule % ?

Best Regards

D
Domingo Bonaobra 👤 Member for 15 years 9 months

Hi Nouraldi,

1. Yes, you got it.

2. Seems your schedule was not resource loaded?

Please let me know.

N
Nouraldin Alqudsi 👤 Member for 9 years 8 months

Hello sir;

Does this picture describe your answer?

and why the WBS has no planned (Schedule) Percent ?

or i should estimate it?

Thanks for your help :)

[[wysiwyg_imageupload:4480:]]

D
Domingo Bonaobra 👤 Member for 15 years 9 months

Hi Nouraldi,

To be able to show the % Planned Complete ( Schedule % Complete in Primavera ), you should maintain and assign baseline to your current schedule.

Hope this helps.

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts