Update baseline

Hello PPers,

What could be the procedure to update a baseline in the recent P6 releases, where the Update button has been erased in the Maintain baseline dialog?

Somebody around me is suggesting to restore the baseline, edit the resulting project, and finally use the project as the "updated" baseline; I am not too confident with that, I would rather downgrade my P6 back to 8.2

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Ranish,

what do you mean by "Professional P6"? are you working with client-server Primavera P6? I am using P6 stand-alone; this could explain the difference

could you please answer my question?

Thank you

R
Ranish KT 👤 Member for 23 years 4 months

We are using P6 professional 15.1, no changes to "update" menu under "maintain baseline" observed as compared to 8.2 or 7.1.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Zoltan,

"No Sir"; I am working on a stand-alone P6 and therefore I have the administrator rights on my PC

Since release 8.3 or 8.4 the "Update baseline" button has been suppressed from the "Maintain baseline" dialog

Z
Zoltan Palffy 👤 Member for 16 years 10 months

that has noting to do with which version that you are using 

1. Make sure that a baseline is truly attached

2. Make sure that you have the proper rights to do this

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts