Hi Guys
i want to know about unit % Complete.in my programm Activities window shows 1.68% whereas Resourece assignment shows 2.23%.whats wrong in my programm?
i attached following pics.
can you explain me details.
Pic-01
Pic-02
Hi Guys
i want to know about unit % Complete.in my programm Activities window shows 1.68% whereas Resourece assignment shows 2.23%.whats wrong in my programm?
i attached following pics.
can you explain me details.
Pic-01
Pic-02
run a global change make sure that
where activity status is not equal to comeplete
then duraiton % complete = physcial % ciomplete
A-1 type task dependent
A-2 Fixed Duration & Units
A-3 Physical % complete
A-4 & A-5 i used default setting.
[[wysiwyg_imageupload:3621:]][[wysiwyg_imageupload:3622:]]
Hard to tell can not see the pics
1. Is the activity type task dependent or resource dependent ?
2. What are you using for duration type ?
3. What are you using for % Complete type ?
4. Under Calcluations do you have Link Actual and actual this period units and costs checked
5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ?