Activity % Complete

D
Diane Jones 👤 Member for 10 years 5 months

Hi,

Can anyone advise why I can't change the 'Activity % Complete'??? I have % Complete Type as 'Physical' and need to update a programme.

I'm new to this and I'm sure it's something simple, help most appreciated.

Thanks,

Diane

Z
Zoltan Palffy 👤 Member for 16 years 10 months

in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level. 

the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete. 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level. 

the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete. 

L
leighton rogers 👤 Member for 10 years 4 months

Hi Diane

 

Im realitivity new to this as well

Have you started the activity? and checked the activity box to started in the status bar? then update the physical % complete

 

regards

 

leighton

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts