Hi,
Can anyone advise why I can't change the 'Activity % Complete'??? I have % Complete Type as 'Physical' and need to update a programme.
I'm new to this and I'm sure it's something simple, help most appreciated.
Thanks,
Diane
Hi,
Can anyone advise why I can't change the 'Activity % Complete'??? I have % Complete Type as 'Physical' and need to update a programme.
I'm new to this and I'm sure it's something simple, help most appreciated.
Thanks,
Diane
in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level.
the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete.
in the % compleyte type you have 3 options physical, units and duration this can be at the individual activity level and can also be set at the project level.
the actvitiy % complete should be equal to whatever the physical, units or duraiton % complete is if not run a global change where activity % complete eqauls physical % complete.
Hi Diane
Im realitivity new to this as well
Have you started the activity? and checked the activity box to started in the status bar? then update the physical % complete
regards
leighton