P6 EPPM Actuals Dissapeared

N
Norman B 👤 Member for 10 years 10 months

Hello all, 

Something bizarre is happening with my P6 project. I am using P6 EPPM, and I was making forecast cost updates. Once i was done with my updates, I noticed all my non-labour actuals had dissapeared. I contacted one of our support guys, who could see all the actuals, and I refreshed my screen and all the actuals suddenly re-appeared. But then I noticed by ETC went wrong. So I ran "Recalculate Assignment Costs" which corrected my ETC but my non-labour actuals dissapeared again. 

Not too sure what is going on. 

Any help is appreciated. 

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

hard to tell not knowing your settings for 

what is your duration type ?

what is your % complete type ?

what is you activity type ? 

how you are updating actual units or costs do you reset Original duraiton and units to remaining ? or do you reset remaing duraiton and units to original ?

are you using store period perforamnce ?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts