Hello all,
Something bizarre is happening with my P6 project. I am using P6 EPPM, and I was making forecast cost updates. Once i was done with my updates, I noticed all my non-labour actuals had dissapeared. I contacted one of our support guys, who could see all the actuals, and I refreshed my screen and all the actuals suddenly re-appeared. But then I noticed by ETC went wrong. So I ran "Recalculate Assignment Costs" which corrected my ETC but my non-labour actuals dissapeared again.
Not too sure what is going on.
Any help is appreciated.
Thanks
hard to tell not knowing your settings for
what is your duration type ?
what is your % complete type ?
what is you activity type ?
how you are updating actual units or costs do you reset Original duraiton and units to remaining ? or do you reset remaing duraiton and units to original ?
are you using store period perforamnce ?