HOW TO EXPORT PRIMAVERA .XER ILE INCLUDING ALL MAINTAINED BASELINES???

A
Ali Murtaza 👤 Member for 10 years 9 months

Dear Professionals,

Is there any way to export xer file including all maintained baselines?

Regards

Ali

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Ali,

until you upgrade to P6 R15, you can easlly export baselines:

1. Restore existing baselines (Project, Maintain baselines, Restore): P6 will create a new project from the baseline

2. Export the current project and the restored baseline from Database 1

3. Import the current project and the baseline to Database 2

4. Create the project baseline in the Database 2 by Project, Maintain baselines, Add, the use the option #2

Be aware that P6 R15 no longer allows to update a baseline; as far as I am concerned, this is a considerable downgrade in the software features, and I will reinstall a previous release (8.3 or 7) of the software

Alexandre

A
Ali Murtaza 👤 Member for 10 years 9 months

Dear Zoltan Palffy,

Thanks, i will definitely upgrade to R.15

Ali

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts