Hi all:
I am a planner from Taiwan, and in a Sabic project by now.
The client requested me to clear all the Unsatisfied Relationship in schedule log.
I tried many times by still can't find a logical way to clear it all.
THANKS FOR YOUR KINDLY HELP~
1. What is the definition of "Unsatisfied Relationship"?
2. How to clear it in schedule log?
Thanks Gong,
I cleared some "unsatisfied relationship" by your way.
I found that A is predecessor and B is successor, A connects to B with FF relationship.
IF B has a actual start, the FF relationship will be defined as "unsatisfied relationship".
Only I can do is to remove the relationship or change the relationship to SS.
Hi, Chen,
I also encountered this problem, and found that when I remove the "SS" relationship linked to the completed activity, the corresponding "Unsatisfied Relationship in schedule log" would disappear. You can have a try.Hope this can help you.