How to clear the "Unsatisfied Relationship" in schedule log?

Hi all:

 

I am a planner from Taiwan, and in a Sabic project by now.

The client requested me to clear all the Unsatisfied Relationship in schedule log.

I tried many times by still can't find a logical way to clear it all.

THANKS FOR YOUR KINDLY HELP~

 

1. What is the definition of "Unsatisfied Relationship"?

2. How to clear it in schedule log?

R
Richard Chen 👤 Member for 11 years 5 months

Thanks Gong,

I cleared some "unsatisfied relationship" by your way.

 

I found that A is predecessor and B is successor, A connects to B with FF relationship.

IF B has a actual start, the FF relationship will be defined as "unsatisfied relationship".

Only I can do is to remove the relationship or change the relationship to SS.

Y
Yanqing Gong 👤 Member for 14 years 2 months

Hi, Chen,

I also encountered this problem, and found that when I remove the "SS" relationship linked to the completed activity, the corresponding "Unsatisfied Relationship in schedule log" would disappear. You can have a try.Hope this can help you.

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts