Duration fraction

Hi,

When i change the presentation of the Duration to be with 2 decimal places, some activities turn out to be not a whole number. For example, i put 6 days for plastering, when i change it to 2 decimal places it gives me 5.75 days......Why ?!

Thanks,

Wadi

Z
Zoltan Palffy 👤 Member for 16 years 10 months

did you import these durations using excel ?

are the druations being derived from manhours  ?

is the activity type resource dependent ?

change them all to whole numbers. I would also venuture to say that your start proect TIME, and your dats date TIME and any constraints that you have that the TIMES are incorrect.

Turn on the times also and check to see if the TIMES are correct

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts