When i change the presentation of the Duration to be with 2 decimal places, some activities turn out to be not a whole number. For example, i put 6 days for plastering, when i change it to 2 decimal places it gives me 5.75 days......Why ?!
Thanks,
Wadi
did you import these durations using excel ?
are the druations being derived from manhours ?
is the activity type resource dependent ?
change them all to whole numbers. I would also venuture to say that your start proect TIME, and your dats date TIME and any constraints that you have that the TIMES are incorrect.
Turn on the times also and check to see if the TIMES are correct