Fellow Plannners,
Can some one here help me with removing the Decimal in BL Project Units Percent Complete? See the pic below

Fellow Plannners,
Can some one here help me with removing the Decimal in BL Project Units Percent Complete? See the pic below

edit
users preference
time units tab
change the unit of time to zero decimals