Actual Finish Date vs Percent Complete

T
Tom Tom 👤 Member for 11 years 9 months

Hello All,

    Is there a way to to claim the completion date for an activity without declaring it 100% complete. Everytime I check the finish date box Primavera automatically declare it 100%. 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you can still give the activity 100% complete and have an actual finish date but leave the cost at a vlaue less than the budgeted amount.

T
Tom Tom 👤 Member for 11 years 9 months

I tired that but it didnt do what I wanted. My EV calculation is based on Physical % complete

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Ah now you have point out the real issue. What you are talking about is unlinking the physical progress from the costs for billing for activities.

Go to the projects directory look at the calculations tab uncheck recalculate actual units when duration % complete changes 

T
Tom Tom 👤 Member for 11 years 9 months

The contract document allows us to claim actual complete date for certain activites without claiming 100% complete so as not to restrain successor activities. This is for activities completed but we can not bill 100%

Z
Zoltan Palffy 👤 Member for 16 years 10 months

what you are asking to do is not logical look at your wording you want to "CLAIM" a completion date but you do not want to say that it is 100% complete. If it is NOT 100% complete then you cannot CLAIM a completion date. This is illogical. What you can do is say that the activity is 100% complete but NOT CLAIM a completion date.

By definition what you are trying to do is not correct.

Is there some reason why you want to do this ? Maybe you need to use suspend and resume or maybe you need to split the activity into 2 activities.

 

Y
Yanqing Gong 👤 Member for 14 years 2 months

Hello Tom,

        you can use the "Physical % Complete" or "Activity % Complete", when you check the finish date box, the progress of these two columns will keep unchanged.

P
Paul Harris 👤 Member for 25 years 2 months

If a task is finished it is 100% complete, if it is not finished it is not 100% complete and all scheduloing sofwtare works this way.

You could use a User Defined Field or the Physical % Complete may be set at 100% with an Actual Start but no Actual Finish.

 

Regards

Paul E Harris

BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner

Managing Director and President

Eastwood Harris Pty Ltd, Australia

http://www.eh.com.auhttp://www.primavera.com.auand http://eastwoodharris.com.

Project Control Consultants and Planning and scheduling software book and training material publishers

Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts