Hello All,
I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout. I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the data is not coming right, How do I do that?
Thanks
Pranab
Dear all,
Did you try in Resources Assignments View ? It should be OK. You can filter for instance by Resource Type =Non Labor. You can add columns dealing with costs. On spreadsheet, you can select costs or units, per period (month, quarter...) or cumulative.
Regards.
Patricia
Hi Schedulers,
Can this not be done? Can we not have a layout with all resource assignment? Has someone designed such a layout?
Thanks,
Pranab