Holding the activity and transferring its resources

I am new to primavera p6. I have a question, I holded an activity i.e suspended from 9-Mar-2014 and resuming on 13-Mar-2014. Now I want to transfering resoruces for on-hold dates to another activity which will finish on 11-mar-2014. After that I will transfer those resources back to original activity.

 

     FL-1420 Temp. Waterline welding 7 3 03-Mar-14 A 13-Mar-14 05:00 PM        FL-2350 Mainline Welding 2 2 09-Mar-14 07:00 AM 10-Mar-14 05:00 PM       FL-2360 Breakup Flange Installation 1 1 11-Mar-14 07:00 AM 11-Mar-14 05:00 PM       FL-2370 Threadolet Installation 1 1 12-Mar-14 07:00 AM 12-Mar-14 05:00 PM  The link I used in FL-1420 I put SS with lag +6 so that activity FL-2350 can start on 09-Mar-2014 during the holding days. But When I put FS on FL-2370 that on 12-Mar-2014 that after completion of this activity it will start Fl-1420 but when i run the schedule the link is giving an error.  Please share your knowledge on this issue.

Thanks

Abdullah Choudhry

R
Raymund de Laza 👤 Member for 16 years 6 months

Abdullah,

Use a resource calendar to assign the resources on the dates you wish them to work.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts