I am new to primavera p6. I have a question, I holded an activity i.e suspended from 9-Mar-2014 and resuming on 13-Mar-2014. Now I want to transfering resoruces for on-hold dates to another activity which will finish on 11-mar-2014. After that I will transfer those resources back to original activity.
FL-1420 Temp. Waterline welding 7 3 03-Mar-14 A 13-Mar-14 05:00 PM FL-2350 Mainline Welding 2 2 09-Mar-14 07:00 AM 10-Mar-14 05:00 PM FL-2360 Breakup Flange Installation 1 1 11-Mar-14 07:00 AM 11-Mar-14 05:00 PM FL-2370 Threadolet Installation 1 1 12-Mar-14 07:00 AM 12-Mar-14 05:00 PM The link I used in FL-1420 I put SS with lag +6 so that activity FL-2350 can start on 09-Mar-2014 during the holding days. But When I put FS on FL-2370 that on 12-Mar-2014 that after completion of this activity it will start Fl-1420 but when i run the schedule the link is giving an error. Please share your knowledge on this issue.
Thanks
Abdullah Choudhry
Abdullah,
Use a resource calendar to assign the resources on the dates you wish them to work.