Hi All,

I want to filter activities between two dates in future, lets say 1June2014 and 30June2014. I am on P6.1, I would want to filter all activities including the ones having early dates inbetween and the ones progressing, i.e. started in April or May and progressing in June of 2014.

Thanks,

Pranab

  

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hi Jean,

Thank you for your reply!

It has to be

 

Early Start < 30June2014

Early Finish > 1Jun2014

 

 

Thanks a lot!

 

Pranab

J
Jean Desjardins 👤 Member for 14 years 7 months

Create a filter "All of the following" with early start less than or equals June 30 2014 and late finish greater than or equals June 1st 2014

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts