Hi All
I’m working on a power station project, and have to input the disruption dates of the “strike action” into my program.
Could someone advise me on how I can show these disruption dates through the entire schedule. I have 4 sets of dates to input into my schedule.
Kind regards
Robert
Robert,
What is the nature of the disuption? -Will it be a case of no work occuring during the strike action, or will the work continue, albeit at reduced productivty?
Hi Robin
Put them on the calendar as non working days
If part working then set up new work patterns to suit.
Best regards
Mike Testro