Inputting disruption dates

 

Hi All

 

I’m working on a power station project, and have to input the disruption dates of the “strike action” into my program.

 

Could someone advise me on how I can show these disruption dates through the entire schedule. I have 4 sets of dates to input into my schedule.

 

Kind regards

 

Robert

G
Gary Whitehead 👤 Member for 17 years 2 months

Robert,

 

What is the nature of the disuption? -Will it be a case of no work occuring during the strike action, or will the work continue, albeit at reduced productivty?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Robin

Put them on the calendar as non working days

If part working then set up new work patterns to suit.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts