Can assign same resource to different activities/projects at same time in p6 v8.2 ???

G
G Abbasi 👤 Member for 12 years 8 months

Hello Every One,

Can we assign same resource (e.g  electircal technician) to differenct projects or withins same project at same time in primavera p6 r8.2.

I am trying to manage my department resources on multiple projects, one resource not to assign multiple acitivities at same time acitivities.

Please help

Thanks 

G
G Abbasi 👤 Member for 12 years 8 months

Thanks for your response,

Exactly i wanted to know that how to prevent to reduce the over-located the resource in multiple activities. 

In MS Project it, if any resource assign to two different activities in between the duration of time, it indicates resource over-located mentioned in figure. But in P6 i didn't found like this.

Can any one know about this to how to do this in P6.

 

[[wysiwyg_imageupload:1811:]]

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello,

Select all the activities you want to assign a specific resource to, then select the resource and click the assign button

Then select on activity at a time to see the assignment in the Activity Details Pane

Alexandre

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts