Dear Planet,
How to produce a report where the total budgeted cost is distributed monthly in P6.1? I am only able to produce a report where the activity budgeted cost shows on the first month and not distributed for the whole period :(
e.g. jan2013 feb2013 mar2013
activity101 $1,000 $1,000 $1,000
my report shows:
jan2013 feb2013 mar2013
activity101 $3,000
Thank you ahead!
Adelfa,
1. Verify the Dates of your resources if it's the same date as your activity.
2. Verify the Calendar used for the Resource, it may be different from the Activity Calendar as well as the Default Calendar.
3. Press F9 to schedule.