Dear all
I had problem with the duration which i was working , there is
what is diffrence between orignal and at copletion duration , how we can use it in primevera
thanks you all
Dear all
I had problem with the duration which i was working , there is
what is diffrence between orignal and at copletion duration , how we can use it in primevera
thanks you all
Hi Rizwan,
The Original duration is the number of working days required to complete each activity based on the current schedule. However, At completion duration is the sum of the actual duration and the remaining duration.
Cheers,
Arnold
hi
Orginal Duration -planned duration
at cmpt duration nothing but actua work performed during project