OPP - Subproject Activities

J
Joanne Foster 👤 Member for 22 years 4 months

I don’t know enough about P3 to make a contribution to which is better, or which is better suited what industry.



I used to be a huge fan of OPP, but since the release of v3 my confidence has gradually reduced to the point where I now have ZERO confidence in anything which Welcom produces.


J
Joanne Foster 👤 Member for 22 years 4 months

open plan is used mostly by defence, there are of course other users, but defence is probably the biggest user of open plan.



P3 is used extensively in Oil & Gas, Mining, Construction etc.



J

O
Oscar Wilde 👤 Member for 20 years 8 months

is open plan very popular in australia seems to be

do you guys not use P3

Have you seen bills comments about knuckheads

Hermie

Help

J
Joanne Foster 👤 Member for 22 years 4 months

You need to go

Project menu > Time Analysis

then ensure that "Actual Date Option" and "Show Summary Dates in Subprojects" is selected (the later is the option will rollsup the dates correctly.



Why on earth you wouldn’t want that happen, and thus make it an option is beyond this little black duck!



J

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts