where is the switch to make % Complete change Remaining Durations? and vice versa

Hello All,

where is the switch to make % Complete change Remaining Durations?

 

My Tasks are set as shown below, but the % Complete field seems to be manually entered, how do I get the % Complete to be auto calculated based on Remaining Duration or vice versa?

Image removed.

P
Paul Harris 👤 Member for 25 years 3 months

In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6.

Regatrds

Paul E Harris

Eastwood Harris Pty Ltd

www.eh.com.au

Featured Partner

Top Posters

yerukalapudi
1 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts

Our Partners