where is the switch to make % Complete change Remaining Durations?
My Tasks are set as shown below, but the % Complete field seems to be manually entered, how do I get the % Complete to be auto calculated based on Remaining Duration or vice versa?
In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6.
Regatrds
Paul E Harris
Eastwood Harris Pty Ltd
www.eh.com.au