where is the switch to make % Complete change Remaining Durations? and vice versa

Hello All,

where is the switch to make % Complete change Remaining Durations?

 

My Tasks are set as shown below, but the % Complete field seems to be manually entered, how do I get the % Complete to be auto calculated based on Remaining Duration or vice versa?

Image removed.

P
Paul Harris 👤 Member for 25 years 1 month

In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6.

Regatrds

Paul E Harris

Eastwood Harris Pty Ltd

www.eh.com.au