Import actual data from Excel to MSP

Dear planners

Is threre any correct way to import actual data from Excel to MSP сurrent schedule?   

Thanks!

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello Ilia

presuming the actual data to be imported are stored in an Excel file with the MS Project Export/import format,

open the file to be updated in MS Project,

select the Excel file in the MS Project File, Open dialog,

select the Update project option

Alexandre