Import actual data from Excel to MSP

Dear planners

Is threre any correct way to import actual data from Excel to MSP сurrent schedule?   

Thanks!

I
Ilia Baranov 👤 Member for 16 years 2 months

Thanks Alexandre!  But i need a correct options for dialog bох? 

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello Ilia

presuming the actual data to be imported are stored in an Excel file with the MS Project Export/import format,

open the file to be updated in MS Project,

select the Excel file in the MS Project File, Open dialog,

select the Update project option

Alexandre