labour

How can we Entre The labour Quantity In Microsoft Project ,i have the laour quantity per day,and i have entered the cost in the Schedule ,Now i want to entry the quantity of labour in schedule .....

S
sai krishna raju 👤 Member for 6 years 10 months

How to assign the Work Resources,Because in that it is Asking Per day cost,the Cost is already loaded in the Schedule.

can you Please send me one Example how to Load the Labour quantity in Schedule.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello,

Insert the filed "Work" in the table you are working it, and enter the labor quantity for each tack;

if you do not assigne Work resources to the tasks, MS Project will not calculate the task duration from the labor quantity.

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts