How can we Entre The labour Quantity In Microsoft Project ,i have the laour quantity per day,and i have entered the cost in the Schedule ,Now i want to entry the quantity of labour in schedule .....
How can we Entre The labour Quantity In Microsoft Project ,i have the laour quantity per day,and i have entered the cost in the Schedule ,Now i want to entry the quantity of labour in schedule .....
How to assign the Work Resources,Because in that it is Asking Per day cost,the Cost is already loaded in the Schedule.
can you Please send me one Example how to Load the Labour quantity in Schedule.
Hello,
Insert the filed "Work" in the table you are working it, and enter the labor quantity for each tack;
if you do not assigne Work resources to the tasks, MS Project will not calculate the task duration from the labor quantity.
Alexandre