labour

How can we Entre The labour Quantity In Microsoft Project ,i have the laour quantity per day,and i have entered the cost in the Schedule ,Now i want to entry the quantity of labour in schedule .....

S
sai krishna raju 👤 Member for 7 years

How to assign the Work Resources,Because in that it is Asking Per day cost,the Cost is already loaded in the Schedule.

can you Please send me one Example how to Load the Labour quantity in Schedule.

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello,

Insert the filed "Work" in the table you are working it, and enter the labor quantity for each tack;

if you do not assigne Work resources to the tasks, MS Project will not calculate the task duration from the labor quantity.

Alexandre

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts