Hi All,
How we can extract report in MS project showing the open end tasks? rather than adding predessor and successor columns.
Regards,
Muataz
Hi All,
How we can extract report in MS project showing the open end tasks? rather than adding predessor and successor columns.
Regards,
Muataz
[Deleted]
Thanks a lot Tom, however I would like to comment that in P6, once you schedule you get a report including the open end tasks.
Best,
Muataz
Alternatively just look for large amounts of float.
Make a new filter called "Open Ends" with the following criteria:
- Predecessors - equals - [empty field]
Or - Successors - equals - [empty field]
For "[empty field]," enter no characters at all.
Then include this filter in your report specification - or just apply the filter in a view.
Note: this is the simplest "open-ends" criteria, same as P6, and does not include dangling starts/finishes. Filtering danglers requires a little macro code ("vba").