Open end tasks

Hi All,

How we can extract report in MS project showing the open end tasks? rather than adding predessor and successor columns.

Regards,

Muataz

M
moutaz aldeib 👤 Member for 22 years 5 months

Thanks a lot Tom, however I would like to comment that in P6, once you schedule you get a report including the open end tasks.

Best,

Muataz

T
Tom Boyle 👤 Member for 19 years 6 months

Make a new filter called "Open Ends" with the following criteria:

- Predecessors - equals - [empty field]

Or - Successors - equals - [empty field]

For "[empty field]," enter no characters at all.

Then include this filter in your report specification - or just apply the filter in a view.

 

Note: this is the simplest "open-ends" criteria, same as P6, and does not include dangling starts/finishes.  Filtering danglers requires a little macro code ("vba").

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts