Split bar

K
Kannan CP 👤 Member for 17 years 11 months

Hi All,

After updating a MS Project Schedule, split bars are visible for the updated activities(i assume due to the logical links). How to avoid it and show a normal current bar for the full remaining duration.

 

Thanks

Best Regards

Kannan

T
Tom Boyle 👤 Member for 19 years 6 months

Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.

T
Tom Boyle 👤 Member for 19 years 6 months

Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts