Split bar

K
Kannan CP 👤 Member for 18 years 1 month

Hi All,

After updating a MS Project Schedule, split bars are visible for the updated activities(i assume due to the logical links). How to avoid it and show a normal current bar for the full remaining duration.

 

Thanks

Best Regards

Kannan

T
Tom Boyle 👤 Member for 19 years 8 months

Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.

T
Tom Boyle 👤 Member for 19 years 8 months

Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.

Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition.  i.e. you don't trust or understand your own schedule logic.  It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts