After updating a MS Project Schedule, split bars are visible for the updated activities(i assume due to the logical links). How to avoid it and show a normal current bar for the full remaining duration.
Thanks
Best Regards
Kannan
Hi All,
After updating a MS Project Schedule, split bars are visible for the updated activities(i assume due to the logical links). How to avoid it and show a normal current bar for the full remaining duration.
Thanks
Best Regards
Kannan
Thanks Tom.
Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.
Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition. i.e. you don't trust or understand your own schedule logic. It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.
Under "Scheduling options for this project:" in the File|Options|Schedule dialog, be sure that "Split in-progress tasks" is not checked, then you will get the behavior you want.
Note: I do not advise or recommend this approach, as you are basically conceding to the "progress override" condition. i.e. you don't trust or understand your own schedule logic. It's better to see where the out-of-sequence progress has occurred, then modify your relationships - if necessary - to reflect the current reality.