Timescale in Microsoft Project 2013

Hi, when I want to show the week numbers on a construction programme in MSP 2013, the "Week 1" always go back to the start of the earliest activity, however I want to show pre-start activities i.e lead in activities before "Week 1" starts and don't seem to have a solution. I could do this very easily in MSP 2010!!!! Can anyone assist?? Thanks  - Paul

R
Ron Beechey 👤 Member for 24 years 1 month

I handled this issue by setting the project start date to week one of the year in the case of 2015 I selected Jan 4.  That week became week 1 and I was looking for my project to start week 22 so I set the start milestone to this date and the weeks read correctly on a gantt chart print out.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts